OFJ Field Journal from Jim Erickson - 10/29/95
A DAY OF MEETINGS
Meetings. Sometimes I feel they are the bane of my existence. Sometimes
I feel they were really productive and necessary. Flying a spacecraft can't
be done without meetings, so you learn to live with them. But whatever you
decide to do for a living, you end up having meetings.
We use meetings to educate ourselves on something, to decide what to
do, or to educate others in the organization. Sometimes we have meetings
to raise our spirits before or during crucial events. We even have meetings
to schedule meetings! This is because some types of meetings require the
same people, and can't happen simultaneously.
As time to Jupiter orbit insertion grows short, meetings seem to increase.
This week is a dramatic example.
Tuesday:
7:45 - 8:00 Read and respond to e-mail messages. E-mail is electronic
mail.
8:00 - 9:00 Meet with project staff and others to decide what changes
to make to the science data gathering that will occur shortly before and
during the probe relay and Jupiter orbit insertion. The meeting ends early
because we have to all go to another meeting:
9:00 - 10:00 All hands meeting. This was a gathering of all the people
on the project. It was to enable the project manager to inform everyone
about the overall decisions on the rapidly changing status of the tape
recorder, and our plans for using it during the probe relay/Jupiter orbit
insertion period.
10:00 - 11:00 Continued the 8:00 decision meeting on what changes to
make to the science data gathering.
11:00-12:30 Command conference. At this meeting the decisions on what
real- time commands are to be sent to the spacecraft for activities that
can't be sent with the stored commands in a sequence load.
12:30 - 1:00 Quick lunch at the cafeteria (BLT on wheat with iced tea).
1:00 - 2:00 Meet with project staff and others to decide what changes
to make to the Critical Engineering Sequence. This is the sequence of
commands that the spacecraft will perform to relay the probe data, and
to fire the main engine to place us into orbit as the first artificial
satellite of Jupiter. This sequence of commands has been extensively verified
and tested, and is designed to continue operating even if really bad things
were to happen to the spacecraft. We take exceptional care, and hesitate
to make even slight changes to this particular sequence.
2:00 - 3:00 Meet with the sequence builders to approve the last sequence
to perform science on Jupiter approach, starting on 11/6/95. It is approved,
and represents the last sequence to be executed on the spacecraft before
arrival at Jupiter.
3:00 - 5:00 Teleconference with the Probe people at Ames Research Center,
discussing the implementation of backup storage of the probe data. All
of the probe data is supposed to be stored on the tape recorder, with
some of the data also stored in Galileo's computer memory as a backup.
Due to the tape recorder difficulties of the preceding weeks, we're increasing
the amount of backup data.
All told, that was 8.5 hours of meetings in one day.
Wednesday was similar. We had an all day review of the project's plans
for arrival at Jupiter, and whether the flight team (the people who work
on the project to fly the spacecraft) are ready. We brought in experienced
people from outside of JPL to look at what we have done to get ready,
and to suggest any improvements. We want them to look for anything which
we might be able to improve, and comment on whether we're ready. We know
we have work left to do, and have plans to finish it all in time. The
review team has to decide if we'll be able to get it all done and be ready
in time.
The review team agrees. We'll be ready!
|