 |
      
      
  

  
|
|
OFJ Field Journal from Lou D'Amario - 11/13/95
SOME TWEAKS ARE BETTER LEFT UNDONE
Jupiter Orbit Insertion (JOI) Tweak
I discussed the JOI tweak (the late update to the size of the JOI maneuver)
in some detail in my last journal entry. The next day, the Navigation
Team was told that the Project was seriously considering eliminating the
JOI tweak (see my last journal for an explanation about tweaks). This
was disappointing, because the JOI tweak is an important part of the overall
navigation strategy for the Jupiter encounter. The problem was that the
Flight Teams were very busy changing the spacecraft sequences because
of the tape recorder problems. There didn't appear to be time for the
Orbiter Engineering Team and the Sequence Team to run through a test and
training exercise for their parts of the JOI tweak development before
arriving at Jupiter.
By Monday November 6, I was able (with the assistance of Mike Wilson
and Chris Potts, who also work on the Navigation Team as maneuver analysts)
to show what would happen if we eliminated the JOI tweak. The first JOI-
correction maneuver at JOI plus one day (called OTM-1, the first Orbital
Trim Maneuver) could get much larger, calling for more propellant. That
was not good, but there was a bigger problem. If for some reason we were
unable to perform OTM-1, the next maneuver (OTM-2) could get so large
(in some situations) that there might not be enough propellant left to
finish the full orbital tour! This became a real dilemma.
On Tuesday, I suggested a possible solution to Ralph Reichert, the Engineering
Office Manager: scratch the JOI tweak test and training exercise, and
keep the JOI tweak in the plan, but only on a so-called "best efforts"
basis. In other words, the Flight Team would try to do the work required
for the JOI tweak in the time we have. Then, if we did manage to get ready
for the tweak (and the JOI tweak was judged to be desirable), the tweak
commands would be sent to the spacecraft. On the other hand, if the work
wasn't finished in time, no commands would be sent, and we would accept
the consequences. What made this strategy feasible was that the exact
same work needed for the JOI tweak had, in fact, already been done once
a few months ago after the Orbiter Deflection Maneuver; it just hadn't
been done on the short timeline of the JOI tweak. As of today, the JOI
tweak is still in the plan (and we have our fingers crossed).
Arrival Day Telecom Meeting
On November 6, I attended the Arrival Day Telecom Strategy Meeting.
This meeting was about how to configure the spacecraft and the DSN (Deep
Space Network) ground antennas to make it as likely as possible that we
will be receiving telemetry (data sent from Galileo) on December 7, the
day that Galileo arrives at Jupiter. There were no major effects on navigation
plans (we lost one tracking pass before the Io flyby, and the backup "uplink
window" (the time period where we send commands up to the spacecraft)
for the JOI tweak was moved later).
Trajectory Change Maneuver 27 (TCM-27)
Starting on November 8, the Navigation Team had one regular working
day (8 hours) to finish working out exactly how great a change in velocity
would be needed for the trajectory change maneuver (TCM-27). This maneuver
improves our aim for when Galileo flies by Io. This work involved the
following steps:
First, the Orbit Determination (OD) Group "generates a solution" (more
on this later) for the spacecraft trajectory (the spacecraft's path) and
the predicted Io flyby conditions using the most recent tracking data
available. Then the Trajectory Analysis (TRAJ) Group checks the OD solution
by mathematically "moving" the spacecraft all the way to Io closest approach
to see if the Io flyby will match the predictions. Since we never get
an exact match, the Maneuver Analysis (MNVR) Group then calculates how
we have to maneuver the spacecraft so that it is perfectly on target (specifically,
they calculate a velocity vector that will correct the miss in the Io
flyby conditions). Once again, the TRAJ Group checks the spacecraft's
trajectory ---but this time with the maneuver added in. If everything
checks out, the Group sends the maneuver information to the Orbiter Engineering
Team (OET); it' s the OET that will translate the Navigation team's request
into actual commands for the spacecraft's thrusters.
Finally, the results of all this work were presented to the Project
managers. Here's a summary of the results. The desired Io closest approach
altitude is 1000 km, and the desired closest approach time is at 17:45:44
UTC on December 7, 1995 (UTC refers to the 24-hour clock time at Greenwich,
or 5:45:44 PM at Greenwich. At JPL, that will be 9:45:44 on the morning
of December 7). Without TCM-27, Galileo would miss its aimpoint at Io
by a predicted 84 kilometers in altitude (a large error), arriving 5 seconds
early. To correct these errors, the spacecraft velocity would have to
be changed by 0.16 meters/second (a small maneuver). Then, at the conclusion
of the presentation, the Navigation Team recommended that TCM-27 be canceled!
Why did we do that? There is some additional information about the maneuver
design process that I haven't mentioned yet.
When the OD Group "solves" for the trajectory, what they are really
doing is finding the trajectory that best "fits" the radio tracking data.
In other words, orbit determination is basically finding the trajectory
that differs as little as possible from the observed tracking data. When
the OD Group determines the best trajectory fit, they are also able to
say how "good" the fit is - i. e., how small the differences from the
observed tracking data are. For TCM-27, the errors in the Io flyby were
small relative to these differences -- we didn't know the miss at Io accurately
enough to say that correcting the errors at TCM-27 would actually improve
the trajectory. In recommending to cancel TCM-27, we were saying that
we needed to wait until the spacecraft got closer to Io and Jupiter so
that the "goodness" of the trajectory solution would improve. The Project
accepted the Navigation Team recommendation, and TCM-27 was canceled.
The next maneuver, TCM-28, is scheduled for November 27 (Io minus 10
days). The design of TCM-28 starts on November 18. We will have 10 more
days of tracking data to reduce the uncertainties of the trajectory (i.
e., improve the "goodness" of the fit). I expect that the Navigation Team
will not recommend canceling TCM-28.
Non-Work Stuff
So far, the increased level of activities at work have not disrupted
my exercise schedule. I am still riding my bike or walking every morning
for 30- 35 minutes; on Saturday and Sunday I go for a longer bike ride
(about an hour). So far, the Navigation Team has not had to work nights
or weekends, but that will change for the upcoming maneuvers and the JOI
tweak. We will be working this coming weekend and the weekend after Thanksgiving.
And there are some all-niters coming. At home, my wife Maria and I are
planning to have some work done on our kitchen - new floors, countertops,
appliances, lighting etc. She will have to assume responsibility for negotiating
with the contractors for this work until after Jupiter arrival - I'm just
too busy right now. I plan to take some vacation time at Christmas. My
mother is coming Barbara, will also be at our house for Christmas.
|
|